Recent Projects
Presbyterian Hospital Central Energy Plant, Charlotte, NC

Challenge:
- Add new boilers and cooling towers, reroute the chilled water pipe, replace pumps and add generators
Scope:
- Demolish the existing steam and chilled water plant and construct ion new steam and chilled water plants without downtime
- Install a boiler plant featuring three 700-horsepower boilers and new associated specialties, and a chilled water plant that included two new 1,500-horsepower chillers, new pumping systems and cooling towers
- Re-route chilled water supply and return pipe with limited shutdown time to the functioning hospital central energy plant
- Add three new generators and all associated fuel piping, exhaust piping, air intake and cooling air
Project Highlights:
- Added new piping and components before disconnecting and removing the existing systems
- Piping systems were fabricated off-site and delivered for installation due to the lack of a laydown area and workspace
- Shutdown time was limited to ensure that the hospital activities were not impacted
- Project was a guaranteed maximum price project, with a profit share component
- Project was delivered seven percent below the estimated cost